Blyth 275 kV — Stella West 2 circuit

SiteBlyth 275 kV substation, Stella West 2 circuit, Northumberland
CustomerNational Grid
Date of applicationSeptember 2010
Pollution typeSaline pollution from the estuary
Equipment3 wall bushings, 275 kV
Duration3 days

The challenge

Stella West 2 faces the same estuary as the rest of Blyth. Salt loads the wall bushings, and the earlier hydrocarbon grease and silicone grease were saturated. A grease that no longer sheds water is not pollution protection. It is the next flashover risk, and it has to be removed before a coating can take its place.

The solution

Three days in September 2010, again from mobile elevating work platforms. The contaminated grease was removed from the three wall bushings and RTV silicone HVIC was sprayed on. The same short outage pattern as Fourstones: clean back to the porcelain, then one hydrophobic film.

The result

The grease was removed and the RTV silicone HVIC coating was completed. National Grid took back a smooth light-grey surface, in place of grease the salt had already defeated.

Before
Before
After
After

Long-term performance

Survey date24 June 2022
CustomerNational Grid
Pollution typeSaline and construction dust
Equipment275 kV, 132 kV and 66 kV insulators, including Stella West circuits

On 24 June 2022 CCS surveyed the whole Blyth substation, including the Stella West circuits. The majority of the insulators carry RTV silicone HVIC, and that coating has given reliable maintenance-free protection for more than 10 years. Salt from the coast and dust from nearby construction are still the pollution. CCS recommended cleaning and an overcoat with RTV silicone HVIC. The photographs are the in-service yard.

In service
In service
In service
In service