Gortawee 110 kV — Quinn cement works
Gortawee 110 kV substation, Quinn cement works, Ballyconnell, County Cavan
ESB
May 2010
Cement dust
3 current transformers, 2 busbar sectionalisers (12 insulators) and 8 support posts, 110 kV

The challenge
Gortawee stands next to the Quinn cement works. Cement dust on a wet porcelain surface can form a tracking path and lead to flashover. RTV silicone HVIC had been in use at Gortawee since 2004, and no flashover had occurred on the coated equipment. This work applied the same protection to new porcelain before it was exposed to the dust.
The solution
Over three days in May 2010 the new equipment was coated at ground level, so a live-bay outage was not required. The porcelain was cleaned, metal sections were shrink-wrapped, and RTV silicone HVIC was sprayed. The sectionalisers and support posts were set on a portable gantry. The current-transformer crates were opened just enough to coat all round. The insulators went to site already protected.
The result
Adhesion and thickness were checked and recorded as sufficient. Coating before installation provides a hydrophobic surface from the day the porcelain is energised.