Application 3

Overcoating air-core reactor coils with Si-COAT 570.

Water beading on a factory-coated air-core reactor coil winding at Sellindge 400 kV converter station, April 2025

Overcoating of air-core reactor coils. Coils are often supplied already coated with RTV silicone HVIC by the OEM at the factory to prevent UV chalking, micro-cracking and corona activity.

CCS Network (ME) Ltd inspects and overcoats these coils in service. Our method statement covers HVIC inspection, removal, new application and overcoating on reactors, capacitors, insulators and associated equipment. If the original coating is known to be ten years old or more, the recommendation is to overcoat at the next available outage.

Documented CCS reactor-coil work

WhenSiteWhat is documented
1–2 October 2020Lincs OFTO, Lincs Substation, adjacent to National Grid Walpole Substation (Transmission Capital)Remove existing RTV silicone HVIC, clean and re-apply to a shunt reactor, with patch repairs on shunt reactors where required.
26–27 October 2020Heysham Substation (Transmission Capital Services)Remove existing RTV silicone HVIC, clean and re-apply to a reactor coil.
October 2020Transmission Investment OFTO, B24Lower coil coating works.
September 2023Transmission Investment OFTO, B24Upper-middle coil coating works.
11–13 March 2024Sundon Substation (National Grid)Remove old RTV silicone, clean and coat one reactor coil with Si-COAT 570.
30 August–16 September 2023Choats Road, Barking, UK Power Networks substation (client Hitachi Energy)Clean, remove existing RTV silicone HVIC if necessary, and re-apply RTV silicone HVIC to two reactor coils.
3 April 2025Sellindge 400 kV converter stationInspection of twelve factory-pre-coated reactor coils (not an overcoat).

These records support a recent programme of reactor-coil inspection and overcoating.